Schedule
Preliminary schedule of the project
Cable Factory modifications
June 2019: Logistic modifications in staircases H and E (loading dock D / E / F and freight lift C / D) and the refurbishment of the Dance House Helsinki rehearsal studio in staircase A will commence.
October 2019: Loading dock D / E / F will be ready for use.
November 2019: The rehearsal studio will be ready for use.
January 2020: The freight lift C / D will be ready for use.
February 2020: The modification of Pannuhalli will commence.
Civil engineering works
October 2019: The civil engineering works for the new building will commence in October and are expected to continue until the end of February 2020.
Construction work of the new building
Summer 2020: The covering of the eastern side of the inner courtyard will commence.
Autumn 2021: Dance House Helsinki and the Cable Factory modifications will be completed.